Client: Landmark Pinnacle

Contractor: Chalegrove Properties

Site: Landmark Pinnacle

Duration: 12 weeks

Scope of Works:

Taking over on this site at short notice we managed to mobilise and deliver a birdcage scaffold that catered for the needs of installing services to the ceiling and keeping ground floor logistics moving.

Independent scaffolds were erected either side of a ground floor walkway. These scaffolds were 1m wide to maximise the space left behind in this busy area.

Beams were spanned overhead and double board and plastic was included to help prevent debris falling through. This was calculated to be heavy duty for storage of materials.

Additional guardrails were included to allow mobile towers to be used on the boarded lift.

The team done very well to mobilise and deliver a high quality and efficient project.

Skip to toolbar